11 Jan, 2016 Author: administrator
After 3 months of securing the relic channel for full water passage, digging the river channel through the western bogs, and casting bridge footings, abutments and wing walls, SumCo was ready to connect the main stem of the new channel with the relic channel. For the moment, the river flows through 2 culverts under the roadway. This is a super-milestone! In the spring, the new bridge will be put in place over a free flowing channel.